Progress Update 4-12-17

The electrician is wrapping up his work in the front duplex. Low voltage installation will happen next, and then we’ll be into installation of insulation and draft-stop. Waterproofing and siding work is underway on the rear duplex of this project, and the electrician has already begun placing boxes in anticipation of being dried in and [...]

By | April 12th, 2017|Uncategorized|0 Comments

Progress Update 4-4-17

Construction continues in earnest on this pair of duplexes. Siding is 90% complete on the front duplex units, and the electrician has begun the wiring for all rough electrical work. In the rear units, window installation is 75% complete and mechanical and plumbing is nearing completion as well. Window installation [...]